This week, we had our first pass at dealing with the city’s final inspection process. Our electrical contractor had a big push to install many of the remaining light fixtures (we don’t have them all yet, but every room now has a fixture to meet code). He also made connections to the new HVAC furnace, installed our rope lighting in the entry way and powder room, and he dug a trench and installed electrical conduit / service to the garage. Unfortunately, the electrical inspector came to site and took issue with the fact that several outlets have small holes next to them (which will be our painters responsibility to apply drywall compound), a disconnect for the future double oven wasn’t installed, and several other items weren’t complete. Therefore, he concluded that it was premature for the electrical inspection and that we’ll have to reschedule. We weren’t expecting a sign off for this pass, but because it is quite common to find issues during the first pass at final inspection, we were hoping the inspector would log his visit on the official permit and write down the items that must be corrected. But this didn’t happen and so we have to complete what we can and reschedule the inspection for a later date. Its likely that we’ll have to call them back a third time before we’ll have our electrical officially signed off on.
On another front, our carpenter was back to install the front and back stairs from the 1st floor to the basement. Until now, we just had the rough plywood stairs for contractors to use, but now our carpenter has installed the final oak wood boards. While on site, he made another small number of correction and installation, included hanging the unit mailboxes.
Our HVAC contractor was back, this time he mounted the steam humidifier on the wall and he installed the radiant piping manifold. The manifold serves as a header pipe that allows for the hot water to flow equally to the multiple zones of radiant tubing that spread out into the basement floor. There is also one additional radiant tube that extends into the floor, but this tube will house the temperature probe to gauge the temperature of the slab. Though the boiler can heat the slab very warm, its important to note that you typically don’t set the slab temperature above 85F because too much heat will start to melt adhesives and seals, especially around toilets, and you can end up with small leaks. We will also keep the slab at least 65F during summer months to make sure that we aren’t creating any moisture conditions that encourage mold growth in the basement.
Finally, a few other noteworthy items that occurred this week: Our woodwork specialist was back at, this time focusing in on the second floor entryway trim-work. We also had our concrete contractor back to rip up the old sidewalk along the side of the building and pour new. In this new sidewalk, we left a little natural dirt spot net to the house, for a future small flower garden. He also poured new concrete for along the foundation wall on the north end of the building and he integrated the metal staircase into the pathway nicely as our previous contractor messed up the correct elevation for the stair landings. Lastly, we installed some landscaping in the front of the building. This included new sod on the street side lot, as well as new sod, bushes, and a Japanese maple in the front yard of the house. Its amazing how much a little landscaping can change the look of a building!