As another week passes, our project starts looking more and more like a house again. This week, we’ve made more substantial progress on finish millwork, HVAC, tile work, and structural work.
At the beginning of the week, our carpenters delivered our interior doors to the building. There are a number of original doors that we have attempted to save, but many required too much restoration for the benefits to be worthwhile. The doors we did save, included beautiful pocket doors (which suffered some damage during the demo process) and three original doors with stained glass inserts. I’ll share some photos of those doors once we get them out of storage and start getting them restored. The doors we did order for our project are solid core unfinished doors. Over the course of the week, our carpenter installed interior doors in both apartments, and continued to work on the finish millwork.
Midweek, we also had our carpenter rip up the old carpet from the main stairwell, so that we could gauge the condition of the woodwork underneath. Luckily, the carpet has seemed to protect the stairs from decades of wear. The carpet itself left many tiny nails / staples that have to be pulled one by one, but once those are removed, our floor guy will sand, stain and poly the stairs back to their formal glory.
Also this week, our tile guy came back through to start water proof lining the basement showers to prep for the upcoming tile work. While on site, he also went back to the 2nd floor bathrooms to install the final finish grout and apply a sealer which should protect the grout and tiles from soap scum and other oily substances from the typical shower products.
Over the weekend, Andrea and I purchased most of the light fixtures for the 2nd floor unit and for one day during this week, our electrician sent out one technician to install them. We went with some basic fixtures in the bedrooms, office and living room. We picked out a ceiling fan for the sun-room, some pendant lights over the future island, and a flashier fixture in the entryway.
Finally, our metal contractor has arrived to start building out the exterior back stairwell and balconies. Our contractor pre-fabricated many of the pieces used for the structure back in his shop. He then delivered the material to our project site and welded them together to create the structure. By the end of the week, the main structural members were installed and at least one protective coat of paint has been applied.











