With the front roof framed out, the initial water tight membrane laid, and the window flashing complete, the building is finally water tight. Our electrical conduit is complete and rough-in inspections for MEP have all been signed off on. Bring on the insulation!
In our on-going effort to use more environmentally safe materials, we decided to go with EcoBatt Knauf Insulation. Their ecobatt product uses a bio-based binder instead of a formaldehyde binder, thereby significantly reducing the number of chemicals leaching into the indoor environment. For our roof insulation, we are going with a fiberglass blown insulation to reach an insulation value of R-49. For our walls, we are aiming to achieve a R-21 value using Fiberglass batts.
Like everything we’ve touched so far in this project, there were a few spots in the house that made insulation a little more difficult. Since we were keeping the trim intact around the dinning room bay windows, we didn’t have the typical wall depth that you get with new framing. The old framing gave us about one inch to work with, so we had to use a rigid board insulation that can give us good protection but can fit the space. In the basement, we are taking a preventative measure by not extending the batt insulation all of the way to the basement floor. Instead, the bottom foot or so of the wall is a moisture resistant rigid foam that, in case moisture does ever collect right at the base of the wall, will resist any mold or rot. Finally, between the 1st floor and the 2nd floor unit, we are installing a layer of sound proofing insulation, which should dampen any sounds between the two units.
It isn’t too difficult to find contractor’s willing to install insulation for a very minimal price. On certain tasks, we have certainly gone with the cheapest bid. For this bid however, we made sure that we are hiring a high quality contractor to do this job right. We went with Minnich Insulation as they had a number of good reviews and were Building Performance Institute, Building Analyst and Envelope certified. In addition to our insulation contractor installing all of the wall and ceiling insulation, he also went through the building sealing all crevasses, outlets, piping penetrations, and other little openings to create a tight air sealed enclosure for our building. As good as the insulation is for our building, without a proper air sealing of the building, the money spent on insulation would be practically wasted. Its the attention to detail, especially while air sealing, that I think makes the biggest difference in quality between insulation contractors. For more on air sealing, see http://www.greenbuildingadvisor.com/air-leaks-waste-energy-and-rot-houses
Finally, with Insulation in full swing, our drywall contractor is preparing to start his work as well. Mid-week, we got a large drywall delivery to the building! Once it gets started, drywall will be installed in a hurry, so we’re looking forward to some big changes in the next week or two!
Insulation arriving on site
We choose to go with Knauf Insulation
2nd Floor walls and Ceiling getting insulated
Drywall gets delivered to site
We used a ridge foam board around dinning room bay windows
Ridge board in the bottom two feet of bsmt wall
1st floor wall insulation and ceiling sound proofing
In-between the beam pocket insulation